The Globe Ledger
Markets. Ideas. A brighter tomorrow.
The Globe Ledgertheglobeledger.com
Tech & Science

Data Centres Are Now an Electricity Story, and the Grid Is the Constraint

The International Energy Agency puts data-centre power use at around 415 terawatt-hours in 2024 and expects it to more than double by 2030. The binding limit on artificial intelligence is turning out to be transformers, transmission lines and permits.
Illustrative photograph: computer server and electronics hardware.

For twenty years the story of computing was that it got cheaper and used less power per task every year, so much so that global data-centre electricity consumption stayed roughly flat even as internet traffic multiplied. Efficiency absorbed growth. That relationship broke around 2022. The International Energy Agency's analysis of energy and artificial intelligence, published in 2025, estimated that data centres used about 415 terawatt-hours of electricity in 2024, around 1.5 percent of global consumption, and projected that figure would reach roughly 945 terawatt-hours by 2030, more than doubling in six years.

The cause is the shape of the new workload. Training and running large AI models is dense, continuous and located in a small number of very large facilities. A single campus of the kind now being built in Texas, Virginia, Ireland or Malaysia can draw as much power as a mid-sized city, and unlike a city it wants that power every hour of the year.

That shifts the constraint from chips to the grid. A data centre can be built in eighteen months. A new high-voltage transmission line in the United States or Europe takes, on average, close to a decade from proposal to energisation, most of it in permitting. Large power transformers, the equipment that steps voltage down for delivery, have lead times measured in years because only a handful of factories make them. Utilities in the most sought-after regions have begun telling developers that interconnection is not available until the 2030s.

The response has been to go around the grid. Developers are signing contracts directly with power producers, financing new gas turbines, buying output from restarted nuclear plants and, in some cases, building generation on site. The economics work because compute is worth more per megawatt-hour than almost any other industrial use, so a data centre can pay a price for firm power that a factory or a household cannot.

That creates a policy problem regulators are only beginning to price. If the largest new electricity customers pay for their own generation and bypass the shared grid, the fixed costs of that grid fall on the remaining customers. If instead they connect to the grid and consume its spare capacity, every other new connection waits longer. Several jurisdictions, including Ireland and parts of the Netherlands, have already paused new data-centre connections in specific areas for exactly this reason.

Water is the second constraint. Cooling large facilities uses water either directly or through the power plants that supply them, and the regions with cheap land and cheap power are frequently the ones with the least water to spare. Operators have moved toward closed-loop and air cooling, at a cost in efficiency.

The efficiency lever has not disappeared. Chips get more useful work per watt each generation, and the industry's own figures show large gains per model per year. But for the first time in the history of computing, those gains are being outrun by demand, and the physical world is setting the pace. Anyone modelling the growth of artificial intelligence over the next five years is, whether they know it or not, modelling the construction schedules of utilities.

This article is for general information only and is not investment advice. Figures are as reported by the cited sources at time of writing.

Related coverage

Illustrative photograph: computer server and electronics hardware.
Tech & Science

The Outer Space Treaty bars national appropriation of outer space: what a satellite operator actually holds is a frequency assignment recorded by the ITU, and a seven-year clock to use it

The 1967 treaty states that outer space “is not subject to national appropriation by claim of sovereignty, by means of use or occupation, or by any other means”, and no instrument consulted here confers title to a point 35,786 km above the equator. What exists instead is a queue run under the ITU Radio Regulations, in which priority is fixed by the date a filing is received and lost if a satellite is not brought into use in time.

Arjun Mehta · September 10, 2026
Illustrative photograph: computer server and electronics hardware.
Tech & Science

An air crash report is not a verdict, and the rules that govern it forbid it from becoming one

The international rulebook for accident investigation, now in its thirteenth edition, states that apportioning blame or liability is not the purpose of the exercise. The organisation most people assume conducts these inquiries almost never does.

Arjun Mehta · September 9, 2026
Illustrative photograph: computer server and electronics hardware.
Tech & Science

World Time Has Been Adjusted Twenty-Seven Times Since 1972. In 2022 the Metrology Conference Voted to Loosen the Rule Behind Them.

Leap seconds keep Coordinated Universal Time within 0.9 seconds of the Earth's rotation, and every one of them has been an insertion rather than a deletion. In 2022 the General Conference on Weights and Measures resolved to raise that tolerance in or before 2035 without deciding what the new value should be, and asked for a plan to be drafted for its 2026 meeting.

Arjun Mehta · September 2, 2026